Renovation holiday home
Belgian Ardennes
Based on the 7 days deal where we remodel one space in 7 days, we were asked by the client to take care of the rental property after the high season and be ready for the autumn holidays. (Do the math…32 working days for 8 spaces…but deadline met of course)……
While several crews were working inside, we were also renovating the outside according to the new insulation standards in force.
The big advantage was that the customer had contacted us in advance, allowing us to prepare all preparatory work and customised furniture in advance.
Renovation works carried out.
- shell of the house and removal of external cladding
- installation of new sustainable techniques
- isolation to the standards 2030
- all furniture was custom-made in advance and checked by the architect before installation
- total make-over in 30 working days
- house delivered before scheduled completion date